Bodegas, corner grocers and restaurants all over the city buy their fruit and vegetables out of a set of warehouses on the Bronx waterfront that went up in 1967, The Real Deal reports. The Hunts Point Produce Market supplies about a quarter of the city's fresh produce, the city says. On Dec. 30, 2025, City Hall announced it would finally rebuild the place. By October the plan was dead, the two administrations were blaming each other, and the merchants who run the market were saying they had their own reasons. Here's who says what, and what happens to the money.

Stock photo by Bence Szemerey on Pexels.
THE MARKET THAT SELLS A QUARTER OF THE CITY'S PRODUCE WORKS OUT OF 1967 WAREHOUSES
The market has roots in lower Manhattan going back to 1790, by its own account, and it moved to Hunts Point in 1967. The city owns the land, more than 100 acres of it. About 26 businesses sell there, most of them family firms, ranging from three employees to about 400, and together they move more than 2.5 billion pounds of produce a year, according to the city's announcement. Gothamist describes them as roughly two dozen families, and says about 1,400 members of Teamsters Local 202 work at the market. Gothamist has also put the market's share higher than the city does, at up to 60 percent of the city's fruits and vegetables. We use the city's own figure.
The buildings are the problem everyone agrees on. Four main warehouses date to 1967, Gothamist reported, and they don't have enough refrigeration. The merchants have run out of room. So up to 1,000 refrigerated trailers sit on the lot running on diesel around the clock, holding produce that doesn't fit inside, the city's development agency told NY1 and Gothamist. Gothamist, citing a state release, says each trailer puts out as much pollution in a day as 330 truck trips on the Cross Bronx Expressway. One in five children in the South Bronx develops asthma. "You can't leave 1,000 diesel trailers running 24-7," City Comptroller Mark Levine told Gothamist.
ERIC ADAMS ANNOUNCED A $635 MILLION REBUILD ON ONE OF HIS LAST DAYS IN OFFICE
The plan had been around for years. In 2023 the state put in $130 million toward what was then estimated at about $650 million, the Bronx Times reported. On Dec. 30, 2025, one of his last days in office, Mayor Eric Adams and the city's Economic Development Corporation announced what they called a historic agreement with the merchants' co-op. Two new all-electric buildings would replace the four old warehouses, and the diesel trailers would go.
The money, from the city's own release: $130 million from the city, $130 million from the state and $145 million in federal grants, including from the Federal Highway Administration. That's $405 million. On top of it, the city expected a federal loan through a Transportation Department program that lends for rail and freight projects. The Real Deal put that loan at $230 million and the total at $635 million; Bloomberg Law ran the same total. Gothamist and City & State have since used about $650 million, with a $225 million loan. The city itself never published a total.
The release also said something easy to miss. The two sides would spend six months working out the design and confirming the co-op's needs could be met "at a financially sustainable cost." Construction was due to start in late 2026. Stephen Katzman, the co-op's co-president, called the agreement "a clear framework for the next phase of work."

Stock photo by Adem Albayrak on Pexels.
SANCHEZ SAYS RENT WAS MORE THAN TRIPLING, AND THE MERCHANTS SAY RENT WASN'T THE REASON
The six months ran out in the summer, and so did the deal. In August, Council Member Justin Sanchez, who represents Hunts Point, told NY1 that the co-op's rent in the new buildings would have gone from $4 million a year to $14 million. The city had first asked for $18 million and came down, he said, and the two sides were still several million dollars apart. "Moving up from $4 million in rent to $14 million in rent is a large jump," he said.
The co-op says that's not why. Its spokesperson, Robert Leonard, told NY1 that rent didn't cause the breakdown and blamed the plan itself: the latest version, he said, "did not allow us to maintain that level of throughput continuously," meaning the merchants couldn't keep moving the same volume of produce while the market was rebuilt around them. Matthew D'Arrigo, a third-generation co-op owner, told Gothamist the two sides kept talking past one another and that city officials didn't seem to understand what it takes to run the market through years of construction. The uncertainty and risk of the deal, he said, "outweighed the risks of not doing it." The co-op voted the plan down over the summer, The Real Deal and Gothamist reported. Neither outlet gives the date or the count.

Stock photo by Alex Grandidier on Pexels.
MAMDANI BLAMES ADAMS FOR RUSHING THE PLAN, AND ADAMS'S DEPUTY SAYS THE BALL WAS DROPPED
City Hall's version starts with the calendar. "The term 'deal' is an overstatement of what the prior administration left us with," Mayor Zohran Mamdani said at an Oct. 14 press conference, The Real Deal reported. He said the framework weakened the city's leverage, because if the co-op rejected it, the current lease would simply be renewed for more years. Deputy Mayor Julie Su told Gothamist the plan was pushed through at the last minute without the buy-in of the people it affected most, and told The Real Deal that announcing a final deal on the way out the door was "cynical at best, irresponsible at worst."
The other side has an answer. Randy Mastro, Adams's first deputy mayor, told Gothamist, "I don't know why the ball was dropped." Gothamist also noted that Mamdani took nearly seven months to name a head for the Economic Development Corporation, the agency running the talks. A mayoral spokesperson, Dora Pekec, said the agency had been "operating at top speed" since day one. Eric Adams himself has not said anything about the collapse that we could find.
Mamdani told WNYC that this version of the plan isn't moving forward but that the city hasn't given up on electrifying or modernizing more of the market. Any new plan will put the co-op's needs and the emissions first, he said at the October press conference, The Real Deal reported. Nobody at City Hall has said what that plan is or when it comes.

Stock photo by Ron Lach on Pexels.
$370 MILLION IN FEDERAL MONEY IS IN JEOPARDY, AND THE COUNCIL'S HEARING HAS NO DATE
The money is where this gets expensive for everyone else. About $370 million in federal grants and loans is now in jeopardy, Gothamist reported on Oct. 22: the $145 million in grants plus the $225 million loan. In September, Gothamist reported that the Transportation Department had already taken Hunts Point off its list of funded projects in the pipeline. The grants and the loan were both meant to pay for building the new market. Whether the grants have been formally taken back, and whether there's a deadline to save any of it, isn't on the record. Nate Bliss, who negotiated the plan for the Adams administration, warned in a City & State op-ed that the money gets more vulnerable as deadlines pass, but he didn't name a date. Neither the city nor the state has said what happens to its own $130 million.
The City Council wants answers. Council Member Virginia Maloney, who chairs the economic development committee, will lead a hearing on how the plan fell apart, Gothamist reported, and Speaker Julie Menin called the project "mission critical." Sanchez called it the city's biggest environmental justice investment. As of Nov. 10 no date has been set. A Council hearing can question officials and put their answers on the record. It can't sign a lease, and it can't bring back federal money.
So here's where it stands. The market that feeds a quarter of the city still works out of 1967 warehouses with diesel trailers idling outside, next to a neighborhood where one kid in five has asthma. One mayor announced a rebuild in his last days in office with six months of homework still undone. The next one let it die and blamed the first. The merchants said no and say rent wasn't the reason. The bill for the delay goes to Hunts Point.
SOURCING
City of New York, Office of the Mayor, Dec 30, 2025 (the agreement; $130 million city, $130 million state, $145 million federal grants including the Federal Highway Administration; the anticipated Railroad Rehabilitation and Improvement Financing loan; 25 percent of the city's fresh produce; about 26 businesses from three to about 400 employees; more than 2.5 billion pounds a year; six months to confirm needs "at a financially sustainable cost"; construction late 2026; Stephen Katzman's remark): nyc.gov
NYCEDC, Dec 30, 2025 (same funding split, 25 percent, about 26 businesses, the aging facility, Aurora-Primus conditionally selected): edc.nyc
The Real Deal, Dec 31, 2025 ($635 million total, $230 million in federal debt, a quarter of the city's produce serving restaurants, bodegas and independent grocers): therealdeal.com
Bloomberg Law, Myles Miller, Dec 30, 2025 ($635 million project in the headline, $405 million in city, state and federal funding): news.bloomberglaw.com
The Real Deal, Ben Miller, Oct 15, 2026 (Mamdani's "overstatement" and the lease renewal; Julie Su's remark; more than $635 million; $405 million plus a $230 million loan; four warehouses into two; the co-op's summer vote; construction slated for late 2026): therealdeal.com
NY1, Kelly Mena, Aug 20, 2026 (Sanchez on $4 million to $14 million and the $18 million first ask; Robert Leonard's denial and his words on throughput; 26 businesses and 25 percent, per the city; nearly 1,000 diesel trailers, per NYCEDC): ny1.com
Gothamist, Elizabeth Kim, Sept 29, 2026 (the co-op's vote; Matthew D'Arrigo; $145 million in grants and a $225 million loan; the Transportation Department pipeline list; Dora Pekec; Julie Su; Randy Mastro; warehouses built in 1967; up to 1,000 trailers; 1,400 Teamsters; one in five children with asthma; the rent going from $4 million to $14 million): gothamist.com
Gothamist, Elizabeth Kim, Oct 5, 2026 (Mamdani on WNYC; Mark Levine; the 330 truck trips, citing a state release; as much as 60 percent of the city's fruits and vegetables): gothamist.com
Gothamist, Elizabeth Kim, Oct 22, 2026 (the planned hearing, not yet scheduled; Virginia Maloney; Julie Menin; Justin Sanchez; Mark Levine's quote; about $370 million in jeopardy; the 1960s warehouses short on refrigeration; more than 100 acres; nearly seven months to name an EDC head): gothamist.com
City & State New York, Nate Bliss, Oct 2, 2026 (opinion: about $650 million, a $225 million loan, 25 percent of fresh produce, funding at risk as deadlines pass): cityandstateny.com
Bronx Times, June 2, 2023 (the state's $130 million toward about $650 million): bxtimes.com
Hunts Point Produce Market, Who We Are (roots to 1790, the 1967 move to the Bronx): huntspointproducemkt.com